Not a to report on the sprinkler project took place yesterday. It rained the first part of the morning meaning I wasn’t able to really get started until almost 10:30. I was able to finish the tunneling under the wires with only a medium amount of frustration, so that was nice. The rain made the ground a little more workable and the heat a LOT more tolerable so that was a nice side affect of the rain.

Once the tunnels were burrowed, it was just a matter of laying the pipe down and gluing it all together. It was rather surprising just how much time it took to glue the pipe all together. Hopefully, I’ve done a good job and everything will stick!

I was also able to get the controller installed in the garage and the wires stretched out to the valves, I’ll hook the valves up to the wires first thing this morning. Here’s a list of the remain tasks.

1) Attach valve wires

2) Test system for leaks.

3) Attach Sprinklers

4) Cover up trenches

5) Install Rain Detector ( still might have to be delayed since it gets installed on the roof)

There’s not a lot to show visually about the difference from yesterday to today, so here’s a picture of the remaining parts in my house.

IMG_7441


Share/Bookmark